Construction key points of external insulation system of rock wool outside wall-3

- Mar 13, 2018-

Construction key points of external insulation system of rock wool outside wall-3


●  rock wool board should be stickable by stick method or point sticking method, and the coating area should not be less than 50%. Rock wool board wipe the adhesive after the first heat insulation plate and the lower end of the paste, rock wool board from the bottom to the top along the horizontal direction of the transverse paving, and should take the edge border anchor slab should be close to nature, plate gap should not be more than 2mm, such as the width of 2mm, and should be filled with insulation materials, the adjacent panel should be flush plate height shall not exceed 1.5mm.


11. 所有穿过岩棉板的穿墙管线与构件,其出口部位应用相同材料填实后进行防水密封处理。

●  all through the pipeline and wall rock wool board member, the export part of the same material filled application after sealing treatment.


12. 如在施工过程中发现贴面层脱落,应及时采取粘结或者用锚固件锚固的方式固定,并及时进行外饰面层施工。

●  as in the construction process found in the veneer layer off, should be taken promptly or fixed by bond anchoring, for exterior surface construction and timely.